525 kV HVDC Cable Production Begins for Germany's Offshore Wind Grid Connection

2026-11-23

Neueste Unternehmensnachrichten über 525 kV HVDC Cable Production Begins for Germany's Offshore Wind Grid Connection

HALDEN, Norway, 16 October 2026 — Cable production has begun for the LanWin2 offshore grid connection project, marking the first industrial-scale manufacturing of Nexans’ 525 kV HVDC cross-linked polyethylene (XLPE) subsea cable technology. Nexans and German transmission system operator TenneT started production at the company’s manufacturing facility in Halden, Norway.

The expansion of offshore wind power is creating new demands for long-distance electricity transmission. As offshore wind farms move farther from shore and transmission capacity increases, high-voltage direct current (HVDC) technology is becoming an important solution for connecting large renewable energy resources to onshore power grids. The LanWin2 milestone reflects more than an increase in manufacturing activity. It also highlights the engineering requirements involved in developing, qualifying and operating advanced high-voltage DC cable systems.


1. LanWin2: A Major Step in Offshore Wind Grid Development

The LanWin2 project is designed to connect offshore wind generation in the German North Sea to the country’s onshore transmission network, and is expected to be commissioned in 2031. According to the project announcement, the start of manufacturing marks the transition from technology qualification and engineering to industrial-scale production and delivery.

The development is part of Europe’s wider effort to expand offshore transmission infrastructure and integrate larger volumes of renewable electricity into national power systems. For offshore wind projects, generating electricity is only one part of the challenge. Reliable transmission links are equally important, particularly when electricity must travel long distances between offshore generation sites and onshore grids.


2. Why 525 kV HVDC Technology Matters

HVDC transmission is widely used in applications where large amounts of electricity need to be transferred over long distances, including offshore wind connections and interregional power links. Compared with conventional HVAC transmission, HVDC offers several advantages in suitable applications:

  • Long-distance transmissionHVDC can be an effective solution for transferring bulk power over long distances, particularly through submarine cables.
  • Reduced charging current constraintsDC cables do not experience the continuous capacitive charging current associated with AC cable operation under normal steady-state conditions.
  • Interconnection flexibilityHVDC links can connect power systems operating at different frequencies or independently controlled operating conditions.
  • Controllable power transferConverter stations allow operators to regulate power flow through the transmission link.

The development of higher-voltage extruded cable systems is particularly important for large offshore wind projects. For a given transmission power, increasing voltage can reduce the current required, subject to the system design. This can help improve the technical and economic performance of long-distance transmission links. However, higher operating voltages also place greater demands on insulation materials, cable accessories and the overall system design.


3. Understanding 525 kV HVDC XLPE Cable Technology

XLPE, or cross-linked polyethylene, is an insulation material widely used in modern power cables. In HVDC applications, XLPE cable systems must withstand continuous DC electrical stress as well as thermal and transient stresses associated with operating conditions. Their performance depends on several interacting factors.

Electrical Insulation and Space Charge

The insulation system must maintain reliable dielectric performance under long-term DC voltage stress. Unlike AC cable insulation, DC insulation is affected by space-charge accumulation and changes in electric field distribution associated with temperature and electrical conductivity. These characteristics make the design and qualification of HVDC XLPE insulation particularly demanding.

Thermal Performance

High-power transmission produces heat in the cable conductor. The resulting temperature distribution depends on conductor loading, insulation properties and the surrounding installation environment. For submarine cable systems, installation conditions and heat dissipation must be considered as part of the overall thermal design.

Cable Accessories and Connections

A cable system is not made up of the conductor and insulation alone. Joints and terminations are also critical components. Their insulation interfaces and electrical field distribution must be compatible with the cable design. A reliable HVDC connection therefore requires the complete cable system, including its accessories, to be evaluated rather than treating the cable itself as an isolated component.


4. How HVDC Cable Systems Are Tested and Qualified

For high-voltage DC transmission, testing is an essential part of technology development and system qualification. The objective is not simply to confirm that a cable can withstand a particular voltage for a short period. Testing must provide evidence that the complete cable system can perform reliably under its intended electrical, thermal and installation conditions. The qualification process generally involves several types of evaluation.

Test stagePurpose
Development testingPerformed during the design and engineering process, helping manufacturers understand material properties, insulation behaviour and the influence of manufacturing variations.
Prequalification testingDemonstrates the long-term performance of a cable system under demanding electrical and thermal conditions before a new design enters commercial service.
Type testingEvaluates whether a specific cable system design meets the required performance characteristics, including its accessories.
Routine and sample testingVerifies that manufactured components and cable lengths meet production requirements and that quality remains consistent.
After-installation testingConfirms that the cable system has not suffered damage during transportation, installation or accessory assembly.

The complete test programme should be established according to the cable design, project requirements and applicable technical recommendations.


5. Technical Challenges in Testing 525 kV HVDC Cable Systems

Testing an advanced HVDC cable system involves more than simply increasing the voltage level of conventional cable testing equipment. Several technical issues require particular attention.

  • Space charge and electric field distributionSpace charge can influence the electric field distribution within polymer insulation. Its behaviour under DC voltage and temperature gradients is an important consideration in HVDC cable design and qualification.
  • Thermal stabilityCable insulation performance is affected by temperature. Testing must consider the thermal conditions expected during operation, including temperature differences along the cable system.
  • Joints and terminationsAccessories are critical parts of the transmission system. Their electrical and mechanical performance must be evaluated together with the cable design.
  • Installation conditionsBurial conditions, installation methods, mechanical stresses and thermal surroundings can all affect system performance.

For cable systems above 400 kV, CIGRE Technical Brochure 852 introduces additional considerations, including thermal stability testing for its defined EHVDC category. The brochure provides recommendations for testing extruded-insulation DC cable systems, including land and submarine cable installations, at rated voltages up to and including 800 kV.


6. Testing Throughout the Cable System Lifecycle

Cable manufacturing is only one stage in the lifecycle of an offshore HVDC transmission system. A project also requires coordinated work involving cable transportation, offshore installation, jointing, termination, commissioning and long-term operation. Quality assurance therefore needs to continue beyond the factory. Key stages include:

  • Design and qualificationVerify the cable system design and demonstrate its electrical and thermal performance.
  • Factory productionControl manufacturing processes and conduct the required routine and sample tests.
  • Transportation and installationManage mechanical handling, cable laying, jointing and termination quality.
  • CommissioningCarry out appropriate post-installation tests before the system enters service.
  • Operation and maintenanceMonitor asset condition and apply suitable inspection and maintenance strategies throughout the service life.

Each stage addresses different risks. Factory tests help verify manufacturing quality, while installation checks and site testing help identify potential damage or defects introduced during project execution. A well-planned testing programme provides continuity between manufacturing, installation and operation.


7. Electrical Testing Across the Wider Power Network

Large offshore transmission projects depend on specialized cable engineering, but the reliability of the wider electricity network also rests on many other electrical assets. Distribution cables, power transformers, switchgear and protection systems all have their own inspection and testing requirements. Their condition needs to be evaluated during installation, commissioning and routine maintenance.

Different equipment calls for different testing approaches. Cable fault location helps maintenance teams investigate underground cable faults. Transformer diagnostics provide information about the condition of transformer windings and insulation systems. High-voltage testing helps assess insulation performance in suitable electrical equipment. XZH TEST develops electrical testing instruments for these areas, including cable fault location systems, transformer testing equipment and high-voltage testing solutions.

Original SourceNexans — “Cable Production Launched for Major German Offshore Wind Grid Connection”, published October 16, 2026.